PROTECT OREGON, OHIO

Oregon's data center decision is still unfolding. Stay informed and engaged.

We are a data-driven society—that's what this data center is all about. So we're bringing you the data so you can make decisions well-informed.

Share this information:

This is an independent citizen resource, not affiliated with Oregon city government. For official meeting schedules, visit the Oregon City Council page. To watch meetings, visit Oregon's YouTube channel.

What's Happening Now

✅ PROJECT STATUS: EXTENSION LEGALLY CONFIRMED

February 9 vote (3-2): Drake, Pollauf, Hornyak YES; Ackerman, Gibbs NO; Walendzak abstained (conflict of interest); Andrus absent. Acting Law Director Fifer ruled abstention not counted — 3 of 5 votes cast = valid majority. Ohio AG's Office responded (Feb 18, 2026): declined to issue an opinion (municipal law directors are outside their advisory authority), but confirmed the two prior opinions Fifer cited have not been overruled. The AG did not endorse the ruling. Due-diligence period runs through September 30, 2026. [1]

📣 MAYOR'S STATEMENT: "Project Is NOT a Done Deal"

Oregon's mayor issued a public statement (~March 1, 2026) clarifying that despite the law director's ruling, the project is not finalized. The developer must still complete due diligence, secure permitting, and execute a development contract before construction can proceed. (Source: Oregon, Ohio Community Facebook Group — unverified social media post, consistent with factual record)

⚖️ LEGAL CHALLENGE FILED

Resident group Responsible Government 4 Oregon LLC filed Open Meetings Act lawsuit February 4, 2026 against City of Oregon and four council members (Hornyak, Pollauf, Walendzak, Andrus), alleging illegal private communications and lack of transparency in council appointment. [7]

What this means: Developer has until September 30, 2026 for due diligence. Extension is NOT project approval—economic development agreement, CRA agreement, and other ordinances must still pass before land purchase. Project is reportedly 6 months behind schedule. [1]

Key quote: Councilmember Beth Ackerman voted against extension, citing concerns about changes to electrical load study, but confirmed "the project is not dead" after speaking with developer Will Turner. [1]

⏰ MARCH 31, 2026: ORIGINAL DEADLINE

The developer's original due-diligence deadline is March 31, 2026. The law director's ruling extended this to September 30, 2026 — but the legal standing of that ruling remains publicly contested. Natural gas pipeline and emission control permits have not yet been obtained.

  • ~500 MW operational power demand; up to 1,000 MW grid draw at peak
  • $17.3 million land sale (168 acres)
  • 450 MW on-site natural gas generation (planned)
  • $2–3 billion estimated total investment
  • • End user not publicly disclosed as of March 2026
What's At Risk

Oregon's wetlands, watershed, and Lake Erie access are precious natural resources that define our community.

  • • Wetlands habitat and water quality
  • • Lake Erie thermal pollution risks
  • • Noise from industrial operations
  • • Community character and quality of life
  • Cooling system chemical runoff — "closed loop" systems use corrosion inhibitors, anti-scaling agents, biocides, and glycols that can reach the environment through blowdown discharge, maintenance draining, or leaks [See Report]

Note: "Closed loop" describes hydraulic design, not the safety of chemicals inside the system. Residents on private wells should review the full environmental section.

Ways to Participate

Oregon residents have several options for participating in the decision-making process.

  • • Attend city council meetings (public comment periods available)
  • • Contact your City Council member with questions or concerns
  • • Review proposed agreements and permits when available
  • • Learn about Community Benefit Agreements, NPDES permits, and disclosure requirements

Want the Complete Picture?

Read our comprehensive in-depth report covering all aspects of the data center proposal: key players, economic impact, environmental concerns, governance issues, and industry best practices.

The principle behind this work

Organized People
Beat Organized Money.

Money moves fast. It hires lawyers, lobbies councils, and frames narratives before most people know what's happening. The only thing that reliably slows it down is an informed community that refuses to be rushed.

1

Be Informed

Read the actual documents. Know the difference between a signed agreement and a press release. Facts are the foundation of everything else.

2

Speak the Truth

Correct misinformation calmly and with sources. One person who knows the facts and stays polite is worth a hundred who are just angry.

3

Organize

Show up. Bring neighbors. Coordinate who speaks, who asks questions, who follows up. Organized presence changes the room in ways that individual outrage never can.

4

Slow the March

Every delay, every question that demands a real answer, every procedural requirement enforced — that is a win. Time is the one resource money cannot simply buy.

What Oregon Residents Have Already Won

This is not theoretical. Organized, informed residents have already changed the trajectory of this project.

Forced a public vote on the land sale extension

The developer needed a 6-month extension. Community pressure ensured it went to a full council vote rather than being handled administratively.

Exposed the Andrus appointment conflict

Residents researched and surfaced the fact that a new council member was appointed by the very mayor who championed the project, raising legitimate Sunshine Law questions.

Demanded and received a formal Q&A response

Community questions were persistent and specific enough that Capacity LLC submitted a formal written Q&A letter on February 27, 2026 — a level of public accountability that rarely happens without organized pressure.

Kept three major votes still ahead

The Economic Development Agreement, the Community Reinvestment Area agreement, and the street vacation are all still unresolved. The project cannot proceed without them. That leverage exists because residents stayed engaged.

Put the school donation under scrutiny

When the $500K school offer was announced, informed residents immediately identified that the district's own letter used conditional language — and asked for the signed agreement. That question is now public record.

Built a public information record

This site exists because residents believed the community deserved facts, not spin. Every person who reads it, shares it, or cites it in a meeting is part of the organizing effort.

"We are a data-driven society — that's what this data center is all about. So we're bringing you the data so you can make decisions well-informed."

— The mission of this site

📋 UNDERSTANDING THE DEVELOPMENT STRUCTURE

INTERMEDIARY VS. END USER

Capacity Infrastructure LLC is NOT the End User

Capacity Infrastructure describes itself as an intermediary that acquires land, secures permits, and prepares "shovel-ready" sites before transferring them to their client. [4] According to their business model, they are not the company that will ultimately operate this facility.

1️⃣

Capacity Infrastructure
buys land

2️⃣

Secures due-diligence extension
(Feb 9 vote extended deadline to Sept 30, 2026 — NOT a project approval)

3️⃣

Transfers to
UNNAMED END USER

[Analysis] Based on standard development agreements, once the sale closes and permits are approved, the city's negotiating position is significantly weaker.

What We Don't Know

  • ❌ Who is the actual end user?
  • ❌ What are their environmental track records?
  • ❌ Will they honor the developer's promises?
  • ❌ Can they afford to operate sustainably?
  • ❌ What happens if they sell to someone else?

Why This Matters [Analysis]

  • ✓ The city is negotiating with an intermediary, not the final operator
  • ✓ Commitments made during negotiations may need to be structured to bind the eventual operator
  • ✓ The end user has not been publicly disclosed as of March 2026
  • ✓ Based on the project scale (500 MW) and AI focus mentioned by the developer, it could potentially be a major tech company, though this has not been confirmed

DISCLOSURE QUESTIONS FOR FUTURE PROPOSALS

Questions residents may want answered before any future vote:

  • 1. Public disclosure of the end user before the vote
  • 2. Community Benefit Agreement with the actual operator, not the middleman
  • 3. Enforceable commitments that survive the transfer to the final owner
  • 4. Right to renegotiate if the end user changes

[Community Perspective] Many communities facing similar proposals have negotiated Community Benefit Agreements before final approval, when the city's bargaining position is strongest.

The bigger picture

WHAT'S HAPPENING AT THE STATE LEVEL

Oregon is not alone. Ohio's legislature is moving on multiple fronts simultaneously — and the outcome of these state-level battles will directly affect what happens in your community.

HB 646 — Data Center Study Commission

Passed the Ohio House unanimously on March 18, 2026. Creates a 13-member commission to study environmental impact, water usage, grid effects, noise, and local economic impact — and submit non-binding best practices within six months. Now moves to the Ohio Senate.

Why it matters for Oregon: A study commission could establish statewide standards that apply to the Oregon project's permitting process. Democrats argue the commission lacks labor representation.

SB 374 — End New Sales Tax Exemptions

Bipartisan Senate bill introduced March 11, 2026 by Sen. Blessing (R) and Sen. Smith (D). Would prohibit granting new data center sales tax exemptions after October 1, 2027. Referred to Senate Finance Committee. Does not affect existing exemptions already granted.

Why it matters for Oregon: A Senate-side path to ending the subsidy, complementing the House veto override effort. Both aim to remove a key financial incentive for the project.

Sales Tax Exemption — Veto Override Push

Governor DeWine vetoed a budget provision to eliminate Ohio's data center sales tax exemption (in place since 2013). Speaker Huffman is pursuing a veto override requiring 60 House votes, but on March 20 said the vote is delayed to May or June 2026 — he does not yet have the commitments needed. Sen. Kent Smith (D-Euclid) estimates repeal would return $187 million/year to the Ohio general fund.

Why it matters for Oregon: Eliminating the sales tax exemption would remove a key financial incentive that makes the Oregon project attractive to the developer's end client.

HB 706 — Statewide Data Center Tariff

Bipartisan bill that would prohibit utilities from recovering data center infrastructure costs from other customer classes (i.e., regular residents and businesses). Would mandate minimum 12-year contracts and require financial assurance before dedicated facility construction begins.

Why it matters for Oregon: Directly addresses the concern that Toledo Edison/FirstEnergy ratepayers — including Oregon residents — could end up subsidizing the data center's grid infrastructure costs.

~18 Municipalities: Moratoriums Spreading

Maumee (12-month), Waterville city (6-month), Waterville Township (12-month), Monclova Township, and Richfield have all enacted moratoriums. Lake Township (Lucas County) voted March 3 to impose a 12-month moratorium. Monroe Township enacted a similar moratorium on March 9. Plain Township (Stark Co.) approved a 12-month moratorium March 24; Massillon City Council approved a 180-day moratorium April 6; Canton Township (Stark Co.) approved a 12-month moratorium April 11; Cincinnati extended temporary restrictions through end of 2026. Over 20 municipalities statewide are now considering or have enacted temporary bans — a wave of local resistance that reflects the same concerns Oregon residents have been raising.

What this shows: Oregon is not an outlier. Communities across Ohio are using every available tool to slow down and scrutinize data center projects before approving them.

Ohio Senate Democrats introduced a package of approximately six bills on February 9, 2026 aimed at reining in data centers statewide.

Key provisions include: eliminating the sales tax exemption • requiring developers to cover all infrastructure costs • capping water usage at 5 million gallons/day • requiring Community Benefit Agreements • reaffirming local home rule authority to reject proposed projects.

Innovation Ohio Report — March 16, 2026

Progressive think tank Innovation Ohio released a report on March 16, 2026 urging Ohio lawmakers to eliminate data center sales tax breaks and require data centers to build their own power sources. The report argues that without these changes, residential ratepayers face massive electricity price hikes as utilities recover infrastructure costs from the broader customer base.

Why it matters for Oregon: This report directly supports the case for requiring the Oregon developer to cover its own grid infrastructure costs — a key protection residents have been asking for in the EDA. (Source: Ohio Capital Journal, March 16, 2026)

NDA Ban Legislation — Ohio Legislature

Ohio lawmakers are advancing legislation that would ban local officials from signing non-disclosure agreements related to economic development projects. This directly addresses one of the core transparency complaints in Oregon: that NDAs have prevented elected officials from sharing project details with the public they represent.

Why it matters for Oregon: If passed, this would make NDA-based secrecy around future economic development votes illegal statewide. (Source: Cleveland.com, March 2026)

JOBS & WORKER PROTECTIONS

Standing WITH workers by demanding enforceable job guarantees

We Hear You

Union workers are right: people need to work NOW, and construction jobs matter. We're not against those jobs at all.

What we're saying is: if this project is going to happen, then the jobs—both construction and long-term operations—need to be in the contract, not just in the speeches.

Other cities have written in minimum numbers of permanent jobs, wage floors, apprenticeship and local hiring requirements, and tied tax breaks to actually delivering those jobs.

Why a Community Benefit Agreement Protects Workers

Without a CBA:

  • • Developer can bring in contractors from anywhere
  • • No guarantee of local hiring
  • • No wage floors or prevailing wage requirements
  • • No apprenticeship programs for Oregon residents
  • • No minimum number of permanent operations jobs

With a CBA:

  • ✓ Local hiring requirements written in
  • ✓ Prevailing wage guarantees
  • ✓ Apprenticeship programs for local residents
  • ✓ Minimum permanent job counts specified
  • ✓ Tax breaks tied to actually delivering jobs

This Is Solidarity, Not Opposition

We're standing WITH workers by demanding these protections be enforceable, not just promised in a PowerPoint presentation.

Lancaster, PA [5]

$20 million community fund, 100% clean energy, strict job guarantees

West Des Moines, IA [5]

3,000 construction + 400 permanent jobs with wage guarantees

Cedar Rapids, IA [8]

31 full-time jobs minimum at $26.20/hour or higher, tied to tax breaks

[Examples from sources 5, 6, and 8 — see Sources section below]

WHAT RESIDENTS ARE ASKING FOR NOW

[Analysis] The February 9 vote (3-2, with one abstention and one absence) on Ordinance 20-2026 was initially uncertain. Acting Law Director Chynna Fifer subsequently issued a six-page memorandum concluding the ordinance did pass: under Robert's Rules of Order (which Oregon follows), abstentions are not counted as votes cast, making 3 of 5 votes cast a valid majority. The Ohio AG's office responded on Feb 18 but declined to issue an advisory opinion, stating that municipal law directors fall outside their statutory advisory authority. The AG only confirmed that the two prior opinions Fifer cited had not been overruled — it did not endorse or validate the ruling. The extension is now in effect through September 30, 2026. [1] Note: This is the extension ordinance (Ordinance 20-2026), separate from the data center zoning ordinance (Ordinance 2026-01). Below are concerns that residents in other communities have raised when facing similar proposals.

Five Common Concerns from Other Communities [Community Perspective]

1. Public Disclosure of End User

In other communities facing similar proposals, residents have asked for public disclosure of the actual operator before votes. This includes information about who will run the facility, their environmental track record, and financial stability.

2. Community Benefit Agreement with Enforceable Terms

Written commitments, not promises. Lancaster PA secured a $20 million community fund. [5] West Des Moines negotiated 400 permanent jobs with wage guarantees. [5] Examples of what other communities have requested:

  • • Minimum number of permanent local jobs with wage floors
  • • Local hiring requirements and apprenticeship programs
  • • Community fund for infrastructure and sustainable development
  • • Tax abatements tied to job creation—lose jobs, lose tax breaks

3. Individual NPDES Permit with Site-Specific Limits

Ohio EPA's general permit has no nutrient limits, weak thermal controls, and no cumulative impact analysis. Some communities have requested:

  • • Individual permit with Lake Erie-specific thermal and nutrient limits
  • • Mandatory water use caps (not developer estimates)
  • • Public reporting of water usage, discharge temperatures, and pollutants
  • • Cumulative impact analysis considering existing facilities

4. Noise Limits and Setback Requirements

Lancaster PA required 750+ foot setbacks and nighttime noise limits. [5] Some residents have expressed interest in enforceable noise ordinances with continuous monitoring.

5. Performance Bonds and Decommissioning Plans

What happens if the facility is abandoned? Some communities have required upfront performance bonds to cover environmental cleanup, infrastructure repair, and decommissioning costs to protect taxpayers.

Learn From This Process

Taking time to understand what's being proposed, who's behind it, and what Oregon receives in return can help residents make informed decisions.

Transparency and accountability are important factors in community trust.

WHO'S INVOLVED

PROJECT SCALE & SPECIFICATIONS

Power Demand
500 MW

At full build-out

For context, this is more power than many entire small cities use.

On-site generation plans:
  • • Up to 828 MW gas generation capacity
  • • 450 MW by Q2-2027
  • • 378 MW by Q1-2028

Note: Developer later said customer "doesn't want to build a whole lot of on-site gas generation"

Water Usage
20,000-30,000

Gallons per day (developer estimate)

⚠️ Critical Caveat: These are developer estimates, not enforceable permit limits or contract terms.

What's needed: Individual NPDES permit with site-specific limits, not general permit. No individual permit application filed yet.

⚠️ NPDES Permit Concerns:
  • • Wastewater discharge directly to Lake Erie
  • • Risk of harmful algal blooms from treated wastewater
  • • Environmental groups alarmed about pollutant introduction
  • • No individual permit application filed as of Feb 2026
Site Details
~177

Total Acres (if approved)

$18M

Purchase Price

10 years

City spent assembling land

Location: Between Wynn, Corduroy, Wynnscape, Parkway, and Blue Heron Drive. Third Amendment adds ~6 acres on Wynnscape Drive for FirstEnergy switchyard.

LESSONS FROM OTHER COMMUNITIES

Other cities have successfully protected themselves. Oregon can too.

Lancaster, Pennsylvania
The Gold Standard
  • Water use cap: 20,000 gal/day maximum (enforceable limit)
  • $20 million community fund ($10M economic dev, $10M sustainable dev)
  • 100% clean energy commitment
  • Strict noise limits written into agreement
  • Annual public reporting on water, energy, environmental metrics

City refused to approve until developer put everything in writing with penalties for non-compliance.

West Des Moines, Iowa
Microsoft Partnership
  • 100% renewable energy (wind power) requirement
  • $2 billion in taxable valuation generated for the city (Des Moines Register, Feb 2024)
  • 3,000 construction + 400 permanent jobs with wage guarantees
  • Public sustainability reporting annually
  • ✓ Tax abatements conditional on meeting commitments
El Paso, Texas
Meta Data Center
  • Specific water disclosure: 750,000 gal/day initial cap (up to 1.5M gal/day at full buildout) (KTSM / El Paso Times, Sep–Dec 2025)
  • Closed-loop cooling system commitment
  • Annual sustainability reports made public
  • 1,800 construction + 100 operating jobs specified
Cedar Rapids, Iowa
Google/QTS
  • 31 full-time jobs minimum at $26.20/hour or higher
  • Google pays $400,000/year for 15 years
  • QTS pays $18 million over 18 years
  • ✓ Payments and tax breaks tied to performance

If job thresholds not met, they lose tax abatement.

YOU'RE NOT ALONE

Communities across America are demanding accountability from data center developers—and winning.

$64B
In Projects Blocked or Delayed

Nationwide, communities have successfully stopped or delayed data center projects worth $64 billion by demanding transparency and protections. (Source: Data Center Watch, March 2025; corroborated by The Hill, Virginia Mercury, and Data Center Dynamics)

11+
States with Moratorium Bills in 2026

Lawmakers in at least 11 states have introduced moratorium legislation in 2026, and 30+ states have filed 300+ data center bills of all types. (Source: Finance & Commerce, March 2026; MultiState, Feb 2026)

230+
Organizations Call for Moratorium

Over 230 organizations called for a national data center moratorium in December 2025 to address environmental and community impacts.

Right Here in Northwest Ohio

Maumee, Ohio

12-month moratorium passed February 2026

City decided to pause and study impacts before making permanent decisions about data center development.

Waterville, Ohio

6-month moratorium passed December 2025

Village council voted to temporarily ban data centers while evaluating long-term community impacts.

Notable Community Victories

Warrenton & Fauquier County, Virginia: Voters removed every single council member who supported Amazon data center projects in November 2024 elections.
Preble County, Ohio: Developer withdrew after community organized referendum campaign.
Lordstown, Ohio: Village banned all data centers; when developer sued, village switched to temporary moratorium.
New Albany, Ohio: Columbus suburb suing to block 228 "fuel cells" at Amazon data center.

Ohio Constitutional Amendment Petition — Active Now

Ohio Residents for Responsible Development received Ballot Board certification on April 3, 2026 to begin collecting signatures for a statewide constitutional amendment that would ban data centers using 25 megawatts or more. The Ohio Attorney General certified the petition on March 26, 2026.

413,488

Valid signatures required

44 / 88

Counties minimum (5% each)

July 1

2026 signature deadline

📋 SIGN THE PETITION IN PERSON — THIS SATURDAY

Saturday, April 11, 2026 · 10:00 AM – 3:00 PM

Christ United Methodist Church Craft Show

More signing locations coming soon.

Retroactive effect on existing projects is legally uncertain. To volunteer: conserveohio2.com

OHIO LEGISLATURE IS PAYING ATTENTION

Bipartisan momentum is building for data center accountability at the state level.

House Bill 646 (Bipartisan)
Data Center Study Commission

Creates independent commission to study data center impacts and recommend policy changes.

  • 6-month study period with public report
  • 4+ public meetings across Ohio
  • Emergency measure showing urgency
  • • House Speaker Huffman: "a lot of support" within caucus
Status: Passed House 97–0 on March 18, 2026. Now in Ohio Senate, which is proposing to convert the commission into a joint House-Senate legislative committee (legislators only). Sponsors are open to modification.
Senate Democratic Package
7+ Bills for Accountability

Comprehensive legislative package addressing costs, transparency, and local control.

  • Grid Cost Responsibility: Data centers pay full costs, no pass-through to ratepayers
  • End Tax Breaks: Stop new sales tax exemptions
  • Community Investment: Prove local benefits before grid connection
  • Home Rule Protection: Affirm local authority to reject projects
  • Water Caps: 5M gallon/day average limit, annual reporting
Governor DeWine's Position

DeWine: "Data centers ought to pay their own share"

"No one wants to see their household rates go up because of a data center."

What He's Said:

  • • Data centers "important to economic development"
  • • But they should pay fair share of costs
  • • Ratepayers shouldn't subsidize them

What He's Done:

  • • Vetoed 2025 attempt to end sales tax exemption
  • • Veto override delayed to May/June 2026 — Huffman lacks 60 commitments
  • • Senate introduced SB 374 as parallel path to end new exemptions
  • • Huffman: "Everybody else has to pay tax at the lumber yard"

Why This Matters for Oregon

State legislation could establish baseline protections that apply to all Ohio data centers, including Oregon's. But waiting for state action means losing local leverage now.

Best strategy: Demand strong local protections in Oregon's Economic Development Agreement, then support state legislation to raise the floor for everyone.

BEFORE THE NEXT COMPANY ARRIVES

Setting Standards Now, Not Later

This data center proposal won't be the last. Oregon's industrial park on the bay will attract future developers. Instead of reacting to each proposal with NDAs and rushed timelines, Oregon can establish baseline accountability standards that apply to any major industrial development—before the next company comes calling.

This Is a Pandora's Box

Once one data center is approved, others will follow. Oregon needs its ducks in a row now—clear standards for what the community will accept, not reactive scrambling when the next NDA arrives.

Baseline Requirements
What Oregon Should Demand from ANY Developer
  • 1.
    No NDAs During Public Review: Community cannot evaluate proposals they cannot discuss. Confidentiality agreements should not prevent residents from sharing information during the public comment period.
  • 2.
    Proper Permitting Before Approval: Individual NPDES permits, gas pipeline permits, and environmental reviews completed before land sale, not after. No contingencies that let developers proceed without permits in hand.
  • 3.
    Public CBA Negotiations: Community Benefit Agreements negotiated in public with resident input, not behind closed doors. Enforceable terms with penalties for non-compliance, not developer promises.
  • 4.
    Proven Track Record: Developers must demonstrate successful projects elsewhere with verifiable community benefits and environmental compliance. No first-time operators on sensitive sites.
  • 5.
    Ongoing Monitoring & Reporting: Public reporting on water usage, energy consumption, noise levels, and thermal discharge. Independent monitoring, not self-reported data.
Trust But Verify
Accountability Mechanisms

Financial Guarantees

Performance bonds and escrow accounts to ensure developers follow through on commitments. If they don't deliver, community keeps the money.

Third-Party Verification

Independent auditors verify compliance with environmental limits and community benefit promises. No relying solely on developer self-reporting.

Clawback Provisions

If developers fail to meet job creation, wage, or environmental targets, community can reclaim tax breaks or require additional payments.

Sunset Clauses

Agreements expire and must be renegotiated every 5-10 years based on actual performance, not indefinite sweetheart deals.

Why Set Standards Now?

Without Baseline Standards:

  • • Each proposal becomes a rushed crisis
  • • Developers control the timeline and information
  • • NDAs prevent community discussion
  • • "Emergency" ordinances bypass normal review
  • • Community negotiates from weakness
  • • Precedent gets set by worst deal, not best

With Baseline Standards:

  • • Developers know expectations upfront
  • • Community evaluates proposals consistently
  • • Public discussion happens before decisions
  • • Adequate time for environmental review
  • • Community negotiates from strength
  • • Best practices become the floor, not the ceiling

The Time to Set Standards Is Before You Need Them

Once a developer is at the table with a proposal, the pressure is on to approve quickly. Setting baseline standards now means Oregon controls the conversation, not the developer.

INFORMATION FOR RESIDENTS

Examples from other communities

Oregon's industrial park may see future data center proposals. Below are examples of protections that other communities have negotiated. Residents can use this information when evaluating future proposals.

5 Common Protections from Other Communities

Examples from other communities:

Lancaster PA, West Des Moines, and Cedar Rapids negotiated written protections covering end-user disclosure, community benefit agreements, individual NPDES permits, noise limits, and performance bonds. These examples may be useful when evaluating future proposals.

1

Public disclosure of end user

Who's actually operating this? Single-user or colocation? We're negotiating with a middleman.

2

Community Benefit Agreement (enforceable)

Minimum job counts, local hiring, prevailing wage, tax revenue guarantees. Developer pays for grid upgrades, not ratepayers.

3

Individual NPDES permit

Site-specific water discharge limits, thermal pollution caps for Lake Erie, continuous monitoring. No general permit.

4

Noise limits & setback requirements

750+ foot setbacks from homes, decibel limits at property line, continuous monitoring with penalties.

5

Performance bonds

Environmental cleanup bond, job creation bond (forfeit if promises not met), decommissioning bond. Protect taxpayers.

If they won't agree, VOTE NO and bring them back to the table.

They've already invested millions. They'll come back with a better deal. You have leverage NOW—after the vote, you have ZERO.

Ongoing Advocacy

Demand Individual NPDES Permit

Ohio EPA's general permit (OHD000001) has major weaknesses: no site-specific nutrient limits, weak thermal limits, no cumulative impact analysis.

Action: File written petition with Ohio EPA Director Anne M. Vogel requesting individual permit for this site. Oregon City Council can also require individual permit as condition of Economic Development Agreement.

Require Community Benefit Agreement

Demand enforceable protections, not developer promises. CBAs are legally binding agreements that ensure projects deliver tangible benefits to local residents:

Best Practice Framework (Brookings Institution):
  • Local Hiring Requirements: Minimum % of jobs for Oregon residents, with priority for underrepresented groups
  • Workforce Training Programs: Funded apprenticeships and skills development for community members
  • Environmental Mitigation: Binding limits on water, noise, emissions with third-party monitoring
  • Community Fund Contributions: Direct financial support for schools, infrastructure, or public services
  • Transparency Requirements: Public reporting on energy/water usage, employment, and compliance

Specific Demands for Oregon:

  • Water: Mandatory caps (not estimates), public reporting, penalties for overuse
  • Noise: Setbacks (750+ ft), nighttime limits, continuous monitoring with public access to data
  • Energy: Clean energy commitments, limits on gas generation, renewable energy targets
  • Community: Local jobs with living wages, community fund ($500K+ annually), tax revenue guarantees
  • Accountability: Independent oversight, regular public audits, meaningful penalties for violations

Support House Bill 646

Ohio HB 646 would create Data Center Study Commission to examine impacts and recommend policy changes. Contact your state legislators to support this bill.

Join Responsible Government for Oregon LLC

This group filed the lawsuit challenging closed-door decisions and Ohio Open Meetings Act violations. Support their efforts for transparency.

QUESTIONS FROM OREGON RESIDENTS

Addressing concerns raised by our community

ENVIRONMENTAL RISKS TO LAKE ERIE

Thermal Pollution

Data centers discharge heated water. Ohio EPA's draft general permit allows discharge up to 90°F with minimal monitoring.

Lake Erie Context: In 1999 heat wave, Lake Erie temps approached 85°F, nearly forcing Davis-Besse Nuclear Power Station shutdown.

What's needed: Site-specific thermal limits based on Lake Erie's sensitivity, not one-size-fits-all general permit.

Nutrient Pollution

Lake Erie already suffers from harmful algal blooms caused by nutrient pollution (nitrogen, phosphorus).

2014 Toledo Water Crisis: Algal blooms shut down drinking water for 500,000 people.

What's needed: Individual NPDES permit with site-specific nutrient limits, not general permit with no nutrient controls.

Cumulative Impacts

Oregon already has multiple facilities discharging to Lake Erie: wastewater treatment plant, Bay Shore generating facility, and Davis-Besse Nuclear Power Station (~10 miles north).

Ohio EPA's general permit does not consider cumulative impacts from multiple data centers or other facilities discharging into the same watershed.

What's needed: Comprehensive watershed analysis before approving additional discharges to Lake Erie.

SHARE YOUR FEEDBACK

What questions do you have? What concerns you? What would you like to know more about?

Share Your Thoughts
Help us understand what residents are thinking

Note: This feedback is for informational purposes. It helps us understand what residents are thinking but is not verified. All submissions are reviewed by site administrators.

HAVE QUESTIONS OR INFORMATION?

Share your concerns, questions, or additional information with the community

Provide email if you'd like a response. Anonymous submissions are also welcome.

Minimum 10 characters

SUPPORT INDEPENDENT INFORMATION

This site is maintained by an Oregon resident and business owner—not affiliated with any government or political organization.

Why donations matter: Maintaining this resource takes time—researching public records, verifying facts, updating content, and keeping the site running. Your support helps keep this information:

  • Independent - No government funding, no corporate sponsors
  • Ad-free - No tracking, no clickbait, just facts
  • Accessible - Free for all Oregon residents
  • Up-to-date - Continuously maintained with new developments

100% voluntary. This information will always be free. If you find it valuable and want to support independent community journalism, donations help cover hosting costs and research time.

Support Independent Research:

Any amount helps. Thank you for supporting independent community information.

SOURCES & DOCUMENTATION

This analysis is based on public documents and verifiable sources. We encourage you to review these materials yourself and verify the information independently.

City of Oregon Official Documents

  1. [1] City Council Meeting, February 9, 2026 - Watch on YouTube | Toledo Blade coverage: Article
  2. [2] Oregon Industrial Park Data Center Information - City of Oregon Official Page
  3. [3] Purchase Agreement details - Referenced in city council meetings and Toledo Blade reporting | Capacity Q&A Letter, Feb 27, 2026 (PDF)

Developer Information

  1. [4] Capacity Infrastructure LLC - Company Website | Oregon Project Page

Community Benefit Agreement Research

  1. [5] "Why Community Benefit Agreements Are Necessary for Data Centers" - Brookings Institution
  2. [6] Lancaster, PA Community Benefits Agreement (Nov 2025) - LancasterOnline | CBA Draft PDF (City of Lancaster)
  3. [7] Responsible Government 4 Oregon LLC Open Meetings Act Lawsuit (Feb 4, 2026) - Toledo Blade
  4. [8] "Data Center Projects and the Benefits They Promise the Public" - Government Technology

State-Level Policy & Investigations (March 2026)

  1. [9] Ohio Capital Journal: "Ohio lawmakers queue up data center study commission" (HB 646, March 4, 2026) - Ohio Capital Journal
  2. [10] Ohio Capital Journal: "Report urges Ohio lawmakers to nix data center tax breaks and require them to build their own power" (Innovation Ohio, March 16, 2026) - Ohio Capital Journal
  3. [11] CREW: "Data centers are spiking Ohio utility prices. One developer is Trump's business partner" (March 12, 2026) - Citizens for Responsibility and Ethics in Washington (Note: Sajwani connection to Oregon project is unverified)
  4. [12] Policy Matters Ohio: "Another chance to stop data center sales tax exemption" (March 11, 2026) - Policy Matters Ohio
  5. [13] Cleveland.com: "Ohio looks to ban corporate giants from making secret deals with local governments" (NDA ban legislation, March 2026) - Cleveland.com
  6. [14] Alliance for the Great Lakes: "Tell Ohio EPA: New data center wastewater permit puts our waters at risk" (NPDES OHD000001) - Alliance for the Great Lakes
  7. [15] Press Publications: "Ohio Attorney General's Office responds to Oregon's ordinance query" (Feb 18, 2026) - Press Publications

Verify This Information

All claims on this page are based on public documents. We encourage you to:

  • ✓ Review the source documents linked above
  • ✓ Attend city council meetings to hear discussions firsthand
  • ✓ Contact city officials with questions
  • ✓ Visit oregonohio.org for official information

If you find an error, please use the contact form above so we can correct it immediately.

Last Updated: April 9, 2026